SBS and APP modified bitumen roof repair, recover and replacement for McKinney, TX commercial buildings, with hot-work planning and hail-resistant detailing.
Tell us about the building and what you are seeing. We reply with the next practical step.
Open flame on a roof is the constraint that shapes every modified bitumen job. Before the first laps are set, someone has to decide whether the work can be torch-applied above an occupied building, which areas need a cold-applied or self-adhered alternative, and who watches the roof for hours after the crew leaves. That decision comes ahead of the membrane choice, and it is the first thing we settle on a McKinney site.
We install, repair and replace SBS and APP modified bitumen roofs on commercial buildings in McKinney, TX, from retail properties to office and industrial parks. Facility directors can start with three facts: the leak location, the hours the building is occupied and the ways onto the roof. From those we plan an inspection that fits the shift schedule.
Modified bitumen is a factory-made roll of asphalt blended with polymer and reinforced with polyester or fiberglass. Two polymers dominate. SBS, a rubber-like modifier, makes the sheet flexible and able to stretch and recover with the roof. APP, a plastic-like modifier, gives a firmer sheet with good heat resistance. Both are usually installed in two or more plies, with a granulated or coated cap sheet that faces the sun and weather.
The plies can be bonded by torch, by hot asphalt, by cold adhesive or by self-adhering backing. Each method has its own safety requirements, odor profile and repair behavior. The multiple layers give the system redundancy: one ply can be damaged without opening the whole roof to water, a property that matters when a crew is working above an operating floor.
A torch applies flame to the back of the sheet and the substrate, and the surrounding materials, such as wood blocking, foam insulation or an old coating, can ignite. Hot-work permits, fire extinguishers on the roof, a clean work zone and a fire watch after the last torch is shut off are standard parts of the job. In some buildings the owner or insurer prohibits open flame, and a cold-applied or self-adhered system takes its place.
Odor and fumes travel to air intakes. We locate intakes, protect or temporarily shut them with the facility director, and plan work so that kettle fumes or adhesive odor do not reach occupied spaces. For tenants who cannot tolerate smell or noise, the schedule moves those steps to off hours. The sequence is written into the scope, with the fire-watch duration and the person responsible named for each shift.
For the Metroplex the Weather Service treats spring as the worst stretch for severe weather, with large hail, damaging wind, flooding and tornadoes striking somewhere in the region in almost any year. A granulated cap sheet over multiple plies absorbs impact better than a thin single sheet, though stones can still bruise the surface or knock granules loose. A storm somewhere in the region does not prove damage at a given building, so we inspect before we decide.
With Dallas-Fort Worth normals near 96°F on summer afternoons, a dark cap sheet can soften enough to scuff under foot traffic. We record granule loss, blisters, splits and open laps after a storm, and we test the insulation under any impact. A storm damage roof repair file keeps fresh marks apart from old wear, which keeps the scope tied to what the storm did.
Laps that were not fully bonded show as open edges or fish-mouths. Splits appear along insulation joints and at changes in deck level, where movement concentrates stress. Blisters show where trapped moisture or air has lifted the sheet. Flashings fail at walls, curbs and penetrations, where stripping plies or base flashings have separated. Granule loss exposes the asphalt to sunlight, and the exposed layer oxidizes and cracks.
We probe the laps, press on blisters, check flashings and measure how much granule surface remains. For wet insulation, an infrared moisture survey finds where the water sits. A flashing failure at a wall can look like a field problem from inside the building, so the wall base is checked before any large repair is priced.
Local defects on a dry roof are repaired by cutting out the failed area, drying the substrate and setting patches with staggered laps, followed by a matching cap. Where the surface has aged but the plies are sound, an acrylic or silicone coating can renew the roof, and silicone roof coatings or acrylic roof coatings each suit different drainage conditions. If the roof is broadly blistered, split or wet, the answer is removal and a new system.
Code and permit steps travel with the scope. The permit follows the 2024 building and energy codes as McKinney amended them, so insulation and reflectance items are confirmed before a replacement is priced. Tear-off limits and disposal are written next to the repair edges. A multi-ply roof is heavy to remove, so the plan names how debris leaves the roof, where it is stored and how drains are covered while old plies come off, because loose granules and asphalt scraps can clog a drain in a single afternoon.
Torch crews, fire watch and staged material add labor that a cold-applied single-ply may not need, and the price reflects that. The condition of the insulation is the next driver: wet insulation under a multi-ply system has to come out, and a recover over wet material only hides the problem. Penetration count, parapet height and the number of drains each add detail work, and every detail is a place where plies have to be lapped and stripped in correctly.
Production calendars matter as much as material. A facility that runs three shifts can lose a day of work to a weather hold and a second day to a fire watch that cannot start until a delivery arrives. We write those holds into the schedule, price them separately and tie each one to a decision the facility director can make in advance.
Rolled material is heavy, and a kettle or torch crew needs space. We set a staging area, a lift plan and a work zone that keeps pedestrians and vehicles away from the load path. On properties in the 121 District or along Hardin Boulevard and US 380, truck routes and roof access must be confirmed on site, since a city overview of highway access cannot speak for a single building. Weather holds are part of the plan: an open torch area is never left unprotected when rain or wind is forecast.
Share the leak location, operating hours, air-intake locations and access limits. We will inspect the plies and flashings and sequence the work around the building's workday.
Short answers to what owners and facility managers ask before a roof visit.
Yes. Self-adhered, cold-applied and hot-asphalt methods exist. The right one depends on the building's fire rules, the substrate and the odor limits.
Not necessarily. Stones can bruise the surface or knock off granules. We inspect the cap sheet and the insulation under any mark before calling it damage.
SBS is rubber-modified and flexible, while APP is plastic-modified and firmer. The choice depends on movement, heat exposure and how the sheet will be applied.
It continues after the last flame is out, for the period the permit and the insurer require. The scope names the person responsible each shift.
The leak location, occupied hours, air-intake locations and roof access limits. Those four items set the work zone and the hot-work plan.
Send a question about the building and we will reply. Or call 555-555-5555.
